Get In Touch
Cover nov2024 104x80.jpg
Current Issue
section
logo

BHEL commissions two pumping units in Telangana

By Swati Deshpande,

Added 21 May 2019

Designed to lift 89.16 cumecs (cubic metres per second) of water by 105.5 metres

Bharat Heavy Electricals Limited (BHEL) has successfully commissioned two more pumping units (Units 3&4) of 116 MW each, of the 7x116 MW Kaleshwaram Lift Irrigation Scheme (LIS) Package-6 in Telangana. BHEL had earlier commissioned Units 1&2 of the same project in April, 2019. Significantly, the pump for each unit is designed to lift 89.16 cumecs (cubic metres per second) of water by 105.5 metres.

Being developed by the Irrigation & CAD (I&CAD) department of the Government of Telangana, the greenfield lift irrigation project (formerly known as Pranhita Chevella) is located in Peddapalli district of Telangana. In the project, water shall be lifted from Sripada Yellampalli reservoir to Medaram reservoir and will be used for irrigation and water supply in nearby areas, thereby contributing to the overall development of the area and the state of Telangana.

BHEL's scope in the project comprises complete Electrical & Mechanical (E&M) works including design, manufacture, supply and supervision of erection and commissioning of 7 sets of Vertical Pump-Motor sets along with associated auxiliaries. The equipment has been manufactured and supplied from BHEL's manufacturing units at Bhopal, Rudrapur and Bengaluru, while the supervision of erection and commissioning at the site was carried out by the company's Power Sector Southern Region division, Chennai.

END