The aircraft is now ready for undertaking ground runs and taxi trials to be followed by its maiden flight. The ground runs will be conducted with the assistance from the engine OEM at ARDC itself.
The HTT-40 design was adapted to a final decision on engine selection in May 2015 and the first prototype manufacturing is completed followed by this roll out.
In November 2015, the Indian Air Force had issued task directive for the Design and Development of HTT-40.
ARDC also touts HTT 40 as the first ever prototype to be manufactured completely based on a digital mock-up and also by using laser tracked jigs and metal tooling at proto phase itself. Also, the Division has sought active participation of Aircraft Division, Bengaluru which has been identified as the production agency for HTT- 40.
Out of the 90 LRUs on HTT-40, 70 systems are sourced from sister Divisions of HAL which include HAL Lucknow, HAL Hyderabad and HAL Korwa(U.P). The Aero Engine Research & Design Centre (AERDC), Engine Division and HAL Kanpur are participating on the engine integration aspects.
END